NaviGate
  river flow
water drop WELCOME
  river flow
water drop WHAT IS
INSTREAM FLOW ?
  river flow
water drop HOW DO
PEOPLE AFFECT
INSTREAM FLOW ?
  river flow
water drop HOW ARE FLOW
RECOMMENDATIONS
DETERMINED ?
  river flow
water drop HOW ARE FLOWS
IMPLEMENTED AND
MONITORED ?
  river flow
water drop HYDROPOWER
DAMS
  river flow
water drop HYDROPOWER
RELICENSING
  river flow
water drop STAFF
CONTACTS
  river flow
water drop LINKS
TO OTHER
SITES
  river flow
water drop CITIZEN
INVOLVEMENT
  river flow
water drop GLOSSARY
OF TERMS
  river flow
water drop PHOTO
GALLERY
  river flow
water drop SITE MAP
North Carolina Department of Environment and Natural Resources
Division of Water Resources
Instream Flow Unit

  WHAT
IS
INSTREAM FLOW?

Introduction
DWR's role
Other instream uses
Flow volume
Low flow periods
Permitted discharges
Offstream uses
Dams
Riparian rights
Regulations



Introduction

Instream flow is the amount of water needed in a stream to adequately provide for downstream uses occurring within the stream channel. Instream uses may include some or all of the following: aquatic habitat, recreation, wetlands maintenance, navigation, hydropower, riparian vegetation, and water quality.


[ To the top ]


Division of Water Resources' role

The Division of Water Resources has a lead role in the Department of Environment and Natural Resources on issues pertaining to the allocation of water. The Division works closely with other state and federal agencies involved in fisheries, water quality, and recreation when considering what flows are necessary to protect natural resources. Flow requirements are often thought of as minimum flows or releases, but they can also include maximum flow limits for peaking hydropower dams, seasonal releases for fish spawning, or weekend releases for recreation.



Other instream uses

Other instream uses of water will depend on the stream, the intended use, and also may vary by season. Flows which provide adult fish habitat may be significantly different than those needed for successful reproduction during spawning season. Flows for recreational canoeing are more important during warm months, especially on weekends and holidays. Some streams are not suitable for canoeing, and thus would not include this as a component of its overall instream flow need.


[ To the top ]


Flow volume

Flow recommendations are always made in terms of volume of water per unit of time, usually cubic feet per second (cfs). As a point of reference, 1.547 cfs equals approximately 11.5 gallons per second or approximately one million gallons per day. It is important to realize that this is not the same as the current or speed of the water, often measured in feet per second. The resource manager needs to know the volume of water to determine if enough of the stream channel will be submerged for aquatic habitat, if a wastewater discharge can be adequately assimilated, or if enough water is available for offstream use.


[ To the top ]


Low flow periods

Most instream flow impacts are more pronounced during low flow periods. It is during these periods when streams are already at low levels that the demand for water is often highest. The drier, and usually hotter, the weather is, the greater the demand is for irrigating lawns, crops, and golf courses, and for electricity.


[ To the top ]


Permitted discharges

All point source dischargers in North Carolina have conditions in their permits which are based on stream flows. The permit limits provide wasteload assimilation through effluent dilution and reoxygenation of the stream. All wastewater discharges are required to be treated so that water quality standards will still be met when the stream flow is as low as the 7Q10, the lowest flow expected to occur on a particular stream for 7 consecutive days once every 10 years. Obviously this is a very low flow which under natural conditions is the result of drought. Flows less than the 7Q10 may be the result of drought, but also can be caused by water withdrawals or dams which impound water. When stream flow falls below the 7Q10, water quality violations may occur. The Division of Water Quality sets water quality standards and permit limits, and is responsible for enforcement.


[ To the top ]


Offstream uses

Contrasting with instream uses are the offstream demands for water. These include water withdrawals for municipal and industrial water supply, agriculture, aquaculture, and golf course irrigation. Such withdrawals may use a simple pipe, a low diversion weir, or a large dam. A simple pipe withdrawal that removes water from a stream without the necessity of an impoundment is called a run-of-river withdrawal. Structures placed in streams to withdraw water for any purpose may require a permit from the U.S. Army Corps of Engineers under Section 404 of the Clean Water Act.

No instream flow study is required if the water withdrawal for the proposed project is less than 20% of the 7-day, 10-year low flow (7Q10). Withdrawals of this size relative to stream flow are considered to have minimal impacts on physical aquatic habitat. However, to avoid cumulative impacts, project developers should still contact the Division of Water Quality regarding potential concerns for downstream assimilative capacity and maintaining water quality standards.


Withdrawals that are 20% of the 7Q10 or more will require additional analysis. The location of the proposed project and the habitat rating of the downstream aquatic habitat will determine whether a desktop analysis or site-specific instream flow study is used to determine the flow. The N.C. Wildlife Resources Commission does the habitat rating.


[ To the top ]


Dams

Construction of a dam will usually require permits under sections 401 and 404 of the federal Clean Water Act. As mentioned earlier, 404 permits are administered by the Corps of Engineers. Section 401 permits are administered by the Division of Water Quality and may include instream flow requirements. Like run-of-river intakes, withdrawals from an impoundment to serve a public water supply must be approved by the Division of Environmental Health, Public Water Supply Section (PWS). Instream flow requirements or withdrawal limitations may be included as part of the environmental review under the N.C. Environmental Policy Act. This applies to both new and expanding withdrawals.

Dams used for hydroelectric power production may affect instream flows by diverting water out of the natural stream channel by canal or pipe to a powerhouse where turbines are spun, power is generated and the water is then returned to the stream. Although not all hydroelectric dams use this type of diversion, those that do may divert water for a distance of several miles. Hydroelectric dams can also change stream flows if they store water behind a dam and release it at certain times to meet the demand for electricity. This type of project, known as "peaking," can dramatically fluctuate stream flows in a very short span of time.

Instream flow concerns for hydropower projects operated by public utilities are addressed during licensing or re-licensing under the Federal Power Act. State and federal review agencies, including the Division of Water Resources (DWR), provide recommendations to the Federal Energy Regulatory Commission (FERC) regarding instream flows. DWR often acts as the coordinating agency within the Department of Environment and Natural Resources for matters relating to FERC licensing. If a project is not subject to FERC jurisdiction, environmental review may take place either during the project?s application for a certificate of public convenience and necessity (CPCN) from the N.C. Utilities Commission or under the Dam Safety Law, administered by the Division of Land Resources

The Dam Safety Law applies to dams that are 15 feet or more high, and with impoundment capacity of 10-acre feet or more. Dams that do not meet both of these criteria are exempt from jurisdiction under this law unless their failure could result in loss of life or significant property damage. Federally owned and operated dams, as well as dams with federal hydropower licenses are also exempt from this law.

The 1995 General Assembly amended the Dam Safety Law to specify the minimum flow for small hydropower producers that divert water around 4000 feet or less of the natural streambed. At new projects, the required minimum flow to any bypassed reach is the 7Q10 flow or 10% of average flow, whichever is greater. A bypassed reach occurs when the project diverts water around the natural stream channel between the dam and powerhouse discharge.


[ To the top ]


Riparian rights

North Carolina water law is based on the "riparian rights" concept, rather than appropriated water rights. (Appropriated water rights refer to the "first in time, first in right" allocation system used in the western United States.) According to this concept, a riparian owner is entitled to the natural flow of a stream running through or along his land in its accustomed channel, undiminished in quantity and unimpaired in quality, except as may be occasioned by reasonable use of the water by other like owners. Some types of water resource projects are subject to state or federal regulations that establish parameters and procedures to determine what is a "reasonable" use. If a water resource development is not subject to any of these regulations, then a water use dispute could be handled as a civil law matter between riparian owners.


[ To the top ]


Regulations

The following regulations and the associated agency with regulatory authority may be useful for addressing instream flow issues:


State
  • Dam Safety Law ( Division of Land Resources )
  • Water Use Act of 1967 ( § 143-215.11 )( Environmental Management Commission, DWR)
  • Water quality certification under section 401 of the Clean Water Act ( Division of Water Quality )
  • State Environmental Policy Act and rules establishing criteria for an environmental assessment, which may include studies to evaluate environmental impacts.
  • Certificate of Public Convenience and Necessity ( N.C. Utilities Commission )

Federal
  • Permit subject to section 404 of the Clean Water Act ( U.S. Army Corps of Engineers )
  • Federal Power Act ( Federal Energy Regulatory Commission )


[ To the top ]



Please send questions or comments to the Instream Flow Unit, which created and maintains this site.