JORDAN LAKE WATER SUPPLY STORAGE
ALLOCATION RECOMMENDATIONS
March 1997
Environmental Management Commission
Division of Water Resources
Department of Environment, Health, and Natural Resources

Executive Summary
The State of North Carolina has been assigned the
use of the entire water supply storage in B. Everett Jordan Lake and, under
G.S. 143-354(a)(11), can assign this storage to any local government having
a need for water supply storage. Administrative rule T15A: 02G .0500 describes
the specific procedures to be used in allocating the Jordan Lake water
supply storage. The two main criteria for Jordan Lake water supply allocations
are future water needs and availability of alternative water supplies.
Also, the administrative rule requires the Environmental Management Commission
to coordinate the review of any allocation requests with the certification
of any interbasin transfers that maybe required.
The Division of Water Resources received a request
to open the allocation process from the Towns of Apex and Cary in May 1996,
for an increase in their existing water supply storage allocation in Jordan
Lake. This is the first time since the initial allocation in 1988 that
the allocation process has been opened. When such requests are received,
it is Division policy to open the allocation process to anyone interested
in either obtaining a new allocation or an increase in an existing allocation.
When the initial allocations of water supply from
Jordan Lake were made in 1988, 42 percent of the water supply pool was
allocated; however, some original allocation holders have since released
their allocations. Currently, 33 million gallons per day (MGD) of the 100
MGD water supply pool is allocated as shown in Table I. Note that allocations
are actually a percentage of the water supply pool and not a rate of withdrawal.
However, for convenience in this report allocations will be expressed in
MGD, since 100 percent of water supply storage has an estimated safe yield
of 100 MGD.
Applicant |
Current Allocations
(MGD) |
Applicant Requests
(MGD) |
Division of
Water Resources Recommendation
(MGD) |
|||
| Level I | Level II | System Request | Total1 | Recommendation | Total1 | |
| Chatham County | 4.0 | 2.0 | 7.0 | 13.0 | 0.0 | 6.0 |
| City of Durham | 25.0 | 25.0 | 0.0 | 0.0 | ||
| Fayetteville | 20.0 | 20.0 | 0.0 | 0.0 | ||
| Greensboro | 25.0 | 25.0 | 0.0 | 0.0 | ||
| Holly Springs | 4.5 | 4.5 | 0.5 | 0.5 | ||
| Apex & Cary2 | 16.0 | 29.0 | 45.0 | 5.0 | 21.0 | |
| Morrisville2 | 4.5 | 4.5 | 2.5 | 2.5 | ||
| Wake County/RTP2 | 3.5 | 3.5 | 1.5 | 1.5 | ||
| OWASA | 10.0 | No application submitted this round | 10.0 | |||
| Orange County | 1.0 | No application submitted this round | 1.0 | |||
| Totals | 20.0 | 13.0 | 118.5 | 151.5 | 9.5 | 42.5 |
1 This column shows the total allocations if all the current requests or recommendations were approved
2 Allocation is contingent on obtaining an interbasin
transfer certification. The recommendations provided are for informational
purposes and public comment only at this time.
In the current round of allocation, the Division received
a total of 8 applications from local and county governments with a total
request of 115 MGD. A summary of the requests is provided in Table I and
detailed analyses of each application are in the Appendices.
Allocation Recommendations for Jordan Lake Water Supply
The Division's recommendations are as follows:
1. Proceed with a public hearing and allocations as recommended for the following systems:
2. Proceed with a public comment period and with the interbasin transfer certification review for a single combined certificate for the following system
All of the systems that had a zero recommendation
have either a zero or a small deficit or other available alternatives to
meet their projected 2015 water demands. For the Towns of Apex, Cary, Morrisville,
and Wake County/RTP South the Division's recommendations contingent on
obtaining interbasin transfer certifications and are only for informational
purposes and serve as a starting point for doing the necessary environmental
review needed for interbasin transfer certification.
The water supply allocation recommendations are a small
incremental amount that will allow for future rounds of allocations. With
over half the water supply pool remaining, storage is available to accommodate
future water needs in a fast growing region of the State.
Interbasin Transfer
The applicants for which an allocation is recommended
and for which interbasin transfer is an issue include Holly Springs, Morrisville,
Cary/Apex, and RTP South. The potential interbasin transfer amounts for
2000 and 2015, based on maximum day demands (MDD) from Jordan Lake, are
estimated in Table II below. Estimates for both 2000 and 2015 are given
since transfers are projected to decrease after 2000 when the West Cary
WWTP is expected to come on-line in either the Haw or Cape Fear River sub-basin.
Table II. Estimated Potential Interbasin Transfers
| System | Total Recommended
Allocation (MGD)* |
Jordan Lake
Maximum Daily Withdrawal (MGD) |
Potential Interbasin
Transfer (MGD) |
||
| 2000 | 2015 | 2000 | 2015 | ||
| Holly Springs | 0.5 | 0 | 0.8 | 0 | 0.8 |
| Morrisville | 2.5 | 1.8 | 3.6 | 1.8 | 3.5 |
| Cary/Apex | 21 | 20.3 | 38.4 | 17.7 | 15.3 |
| RTP South | 1.5 | 0.9 | 2.6 | 0.7 | 0.0 |
*Includes existing allocation amounts
The interbasin transfer rule stipulates that responsibility
for obtaining certification for a transfer belongs to the party that owns
the pipe where it crosses the sub-basin divide. For all of the systems
listed above, that responsibility would be Cary's and Apex's, since they
own the pipes at the point where the transfer occurs. However, the rules
also allow for another party involved in the transfer to assume responsibility
for certification, if approved by the Director of the Division of Water
Resources.
Holly Springs has requested to assume responsibility
for certification of the interbasin transfer associated with their allocation
request. The Division is going to approve their request for the following
reason: Holly Springs has its own WWTP which discharges back into the Cape
Fear River basin, not the Neuse River basin and the transfer is for a small
amount between sub-basins in the Cape Fear River basin. The estimated maximum
daily transfer is only 0.8 MGD, based on the 0.5 MGD allocation recommendation.
Since the Holly Springs interbasin transfer potential is only 0.8 MGD,
well below the 2.0 MGD certification threshold, no interbasin transfer
certification is needed at this time.
Allocation Contract Revisions
The Division recommends modifying how the contracts between the State and local governments are written. The Division proposes to base the contract solely on the use of reservoir storage, rather than on a maximum rate of withdrawal. This change would make the contract more consistent with what is being purchased. Local governments are purchasing reservoir storage and not a guaranteed rate of withdrawal. This change will allow systems to be able to increase withdrawals to meet their peak demands as long as the annual average withdrawal rate does not exceed their allocation amount and their storage is not depleted. An additional change to protect the reservoir from potential overuse will be to require all systems to have a water shortage response plan completed and approved by both the US Army Corps of Engineers and the State.
Table Of Contents
Executive Summary i
Allocation Recommendations for Jordan Lake Water Supply ii
Interbasin Transfer ii
Allocation Contract Revisions iii
Table Of Contents iv
Background 1
Allocation Criteria 7
Recommendations 9
Watershed and Interbasin Transfers 13
Appendices 18
Appendix A. Chatham County A-1
Overview and System Recommendation A-1
Population and Water Use Projections A-1
Current Water Supply Sources A-3
Alternative Sources A-4
Conservation and Demand Management A-4
Plans to use Jordan Lake A-4
Watershed and Interbasin Transfers A-5
Appendix B. City of Durham B-1
Overview and System Recommendation B-1
Population and Water Use Projections B-1
Current Water Supply Sources B-2
Alternative Sources B-3
Conservation and Demand Management B-4
Plans to use Jordan Lake B-4
Watershed and Interbasin Transfers B-4
Appendix C. City of Fayetteville C-1
Overview and System Recommendation C-1
Population and Water Use Projections C-1
Current Water Supply Sources C-2
Alternative Sources C-3
Conservation and Demand Management C-3
Plans to use Jordan Lake C-3
Watershed and Interbasin Transfers C-4
Appendix D. City of Greensboro D-1
Overview and System Recommendation D-1
Population and Water Use Projections D-1
Current Water Supply Sources D-2
Alternative Sources D-2
Conservation and Demand Management D-2
Plans to use Jordan Lake D-3
Watershed and Interbasin Transfers D-3
Appendix E. Towns of Apex and Cary E-1
Overview and System Recommendation E-1
Population and Water Use Projections E-1
Current Water Supply Sources E-3
Alternative Sources E-4
Conservation and Demand Management E-4
Plans to use Jordan Lake E-4
Watershed and Interbasin Transfers E-5
Appendix F. Town of Holly Springs F-1
Overview and System Recommendation F-1
Population and Water Use Projections F-1
Current Water Supply Sources F-3
Alternative Sources F-4
Conservation and Demand Management F-4
Plans to use Jordan Lake F-4
Watershed and Interbasin Transfers F-5
Appendix G. Town of Morrisville G-1
Overview and System Recommendation G-1
Population and Water Use Projections G-1
Current Water Supply Sources G-3
Alternative Sources G-3
Conservation and Demand Management G-3
Plans to use Jordan Lake G-3
Watershed and Interbasin Transfers G-4
Appendix H. Wake County / Research Triangle Park H-1
Overview and System Recommendation H-1
Population and Water Use Projections H-1
Current Water Supply Sources H-3
Alternative Sources H-3
Conservation and Demand Management H-3
Plans to use Jordan Lake H-3
Watershed and Interbasin Transfers H-4
Appendix I. Summary of Public Comments on the Process I-1
Appendix J. Population and Water Use Projection Methodology J-1
Appendix K. North Carolina Administrative Code Section T15A:02G.0500 Allocation of Jordan Lake Water Supply Storage K-1
.0501 INTRODUCTION K-1
.0502 DEFINITIONS K-1
.0503 FORMAL APPLICATION K-1
.0504 ALLOCATION OF WATER SUPPLY STORAGE K-2
.0505 NOTIFICATION AND PAYMENT K-3
.0506 RECIPIENTS' REQUIREMENTS K-3
.0507 LOSS OF ALLOCATION K-3
Appendix L. North Carolina Statute G.S. 143-215.22G and G.S. 143-215.22I Regulation of Surface Water Transfers L-1
§ 143-215.22G. Definitions L-1
§ 143-215.22H. Registration of water withdrawals and transfers required. L-2
§ 143-215.22I. Regulation of surface water transfers. L-2
Appendix M. North Carolina Administrative Code Section T15A:02G.0400 Regulation of Surface Water Transfers M-1
Appendix N. Contacts For Additional Information
N-1
The Division of Water Resources received a request to re-open
the allocation process from the Towns of Apex and Cary in May 1996 for
an increase in their water supply storage in B. Everett Jordan Lake. This
is the first time since the initial allocation in 1988 that the allocation
process has been opened. When such requests are received, it is Division
policy to open the allocation process to anyone interested in either obtaining
a new allocation or increasing an existing allocation.
Schedule
When the request was received on May 8, 1996, the Division of Water Resources began an extensive notification effort, including:
The Division of Water Resources held a public information
meeting on June 27, 1996 to explain the allocation process in greater detail
and to receive comments about the process. Based upon the applications
received, the Division of Water Resources is making recommendations for
water supply storage allocations in this report. With the approval of the
EMC, a public hearing will be held to discuss the proposed allocations.
After this public hearing, the EMC will make a final decision for allocations
that do not involve an interbasin transfer certificate; allocation requests
involving interbasin transfers will proceed with interbasin transfer certification.
The final step for each applicant receiving an allocation will be entering
into a repayment contract with the State for the water supply costs. These
costs are described in more detail starting on page 5.
A summary of the major steps in the allocation process is
shown in Figure 1. The Division has made an adjustment to the allocation
process in response to the concern about tentative EMC approval of water
supply need becoming a conditional preapproval of interbasin transfer (IBT).
The revised schedule will allow those allocations that do not involve IBT
to proceed as was originally scheduled. For allocations that involve an
interbasin transfer, the EMC decisions on both the allocation and interbasin
transfer certification will be delayed until after the IBT review process
is completed.
Jordan Lake Operations
B. Everett Jordan Lake is a U.S. Army Corps of Engineers
multi-purpose lake in Chatham County. Construction on the dam started in
1967 and Jordan Lake completed filling in 1982. As seen in Figure 2, the
dam is located on the Haw River just downstream of the confluence of the
Haw and New Hope Rivers, with most of the lake's storage being in the New
Hope basin.
The lake is designed to provide for water supply, recreation,
flood control, fish and wildlife management, and flow augmentation to maintain
downstream water quality during natural low flow periods. As is typical
for multi-purpose reservoirs, the lake's storage volume is divided vertically
into several "pools" which are keyed to lake level elevations.
Specifically, there is a flood pool, which provides for flood control storage;
a conservation pool, which provides for water supply and low flow augmentation;
and a sediment pool, which provides for the accumulation of sediment.
The top of the conservation pool corresponds with the normal lake level of 216 feet mean sea level (M.S.L.). At this elevation, Jordan Lake covers 13,900 acres. As Figure 3 shows, usable water in the lake at its normal elevation amounts to a total volume of approximately 140,400 acre-feet(1) and is referred to as the conservation storage. Approximately 45,800 acre-feet in conservation storage, or about 15 billion gallons, is designated to provide water supply. This amount of storage is estimated to be able to furnish approximately 100 million gallons per day (MGD ) during most of the severest droughts.
In
addition to water supply, the lake's conservation storage provides 94,600
acre-feet for downstream flow augmentation to benefit water quality and
economic development. The low flow augmentation storage is used to maintain
a minimum flow of about 388 MGD (600 cfs) at Lillington. The minimum streamflow
recorded by the USGS at Lillington prior to Jordan Lake's impoundment was
7.1 MGD (11 cfs). Storage and releases for flow augmentation are provided
in addition to storage for the 100 MGD water supply. The water supply allocation
has no impact on the low-flow augmentation releases. Neither the low flow
augmentation pool nor the minimum releases will be diminished.
Current Allocations
The State of North Carolina has been assigned the use of
the entire water supply storage in Jordan Lake and, under G.S. 143-354(a)(11),
can assign this storage to local government having a need for water supply
storage. Administrative rule T15A: 02G .0500 (included in Appendix K) describes
the specific procedures to be used in allocating the Jordan Lake water
supply storage. These procedures are outlined below.
Allocations fall into two categories. Level I allocations
are made based on 20-year water need projections and when withdrawals
are planned to begin within five years of receiving the allocation. Level
II allocations are made based on longer term needs of up to 30 years.
Only one round of allocations have been made thus far. These
initial allocations of water supply from Jordan Lake were made in 1988.
At that time, 42 percent of the water supply pool was allocated; however,
some original allocation holders have since released their allocations.
Currently, one-third, or 33 MGD, of the 100 MGD water supply pool is allocated
as follows in Table 1. Note that allocations are actually
a percentage of the water supply pool and not a rate of withdrawal. However,
for convenience in this report allocations will be expressed in MGD, since
100 percent of water supply storage has an estimated safe yield of 100
MGD.
Table 1. Existing Jordan Water Supply Allocations
| Allocation Holder | Level I | Level II |
| Cary-Apex | 16 | 0 |
| Chatham County | 4 | 2 |
| Orange Water & Sewer Authority | 0 | 10 |
| Orange County | 0 | 1 |
| Total | 20 MGD | 13 MGD |
Two of the current allocation holders, Apex & Cary and
Chatham County, are requesting an increase in their existing allocations.
Orange Water & Sewer Authority and Orange County have not requested
an increase and both anticipate starting to use their allocations sometime
between 2010 and 2015.
Existing rules limit water supply allocations that will
result in diversions out of the lake's watershed to 50 percent of the 100
MGD total water supply yield. The EMC may review and revise this limit
based on experience in managing the lake and on the effects of changes
in the lake's watershed that
will affect its yield. Currently, 19.4 MGD of the 100 MGD yield is approved
to be diverted out of the lake's watershed.
Costs and Repayment Requirements
Jordan Lake was financed and constructed by the Federal
government through the U.S. Army Corps of Engineers. Storage space for
municipal and industrial water supply was included at the request of state
and local officials with the understanding that the costs associated with
this water supply storage would be paid for by the actual users. North
Carolina statute (G.S. 143-215.38) authorized the State, acting through
the EMC, to assume repayment responsibilities for these costs. The costs
associated with providing water supply storage in Jordan Lake fall into
three basic categories: capital costs, operating costs, and administrative
costs. The total annual cost for each one MGD allocation out of Jordan
Lake varies with a number of parameters, including when the allocation
is received, when water is actually withdrawn, the length of the payback
period, and variable annual operating expenses. As an example, for each
new one MGD of water supply withdrawal beginning in 1997, the total annual
cost is estimated to be $4136.(2)
An additional administration charge of $250 will be added to each bill
regardless of the total number of MGD allocated.
The two main criteria for Jordan Lake allocations are future water needs and availability of alternative water supplies. Applications contained the following information:
Water demand is computed on an average daily basis to correspond with
the recommended contract changes and reservoir safe yield determination.
The original 30-year planning horizon (the year 2025) has been revised
to a 20-year planning horizon (the year 2015) to allow for greater flexibility
in making future allocations.
Future Water Needs
Applicants provided estimates of water use for the period 1995 through 2025. For each applicant, the Division also performed an independent analysis of future need. The analysis considered factors affecting water demand including:
population growth
service area expansion
conservation
unaccounted water use
interconnections
industrial development.
The independent analysis followed several general steps. First, the
Division estimated future service population out to the year 2025. The
starting point was the Office of State Planning (OSP) population forecast.
In most cases, OSP estimates were modified to reflect additional information
provided by the applicants.
The second step was to develop future per capita water use rates which
include the effects of water conservation, industrial growth, and changing
urban patterns. Conservation savings are expected to result from changes
in plumbing codes, improved system maintenance, customer education, and
adoption of water reuse.
In the third step, the Division estimated future water use by multiplying
estimated service population by the future per capita rate. The analysis
assumed all water use attributable to new population would be consumed
at the future per capita rate. The analysis also assumes that water use
by the current population would gradually attain the future per capita
rate due to fixture replacement and other conservation programs. The Division
assumed "replacement" would occur at an annual rate of 3 percent.
Appendix J contains a detailed explanation of the Division's population
and water use methodology.
The allocation process imposes a cost on both the State and local governments.
Therefore, the Division applied an additional test to be sure applicants
will not need to apply for an increased allocation for at least the next
5 to 10 years (year 2005). The Division used a common rule of thumb for
water supply planning: when a water system's average daily demand is at
or exceeds 80 percent of the available yield, then a system needs to start
expansion of their existing supplies. The Division applied this rule of
thumb to the applicants' 2005 projected average daily water demands to
determine if there was adequate water for the next 10 years.
Alternatives
Applicants were required to provide information on alternative water
supplies that could be developed in lieu of a Jordan Lake allocation. Alternatives
may include bulk purchases from other suppliers, new reservoir and well
development, and reservoir expansion. The list of alternatives should have
included all potential sources that the system had previously evaluated.
Systems were not required to perform new feasibility studies of other potential
supplies. The Division evaluated each alternative based on financial cost
and institutional difficulty of developing the resource in comparison with
a Jordan Lake withdrawal. The Division also considered the impact of each
alternative on interbasin transfer and other environmental impacts.
In cases where a system has a viable alternative to Jordan Lake, the
Division has recommended an adjustment in the allocation request to account
for the alternative supply. Appendices A-H include a discussion of alternative
water supplies for each applicant.
Allocation Recommendations
The Division of Water Resources used a conservative allocation criterion that allocates water for short-range needs (20 years). This ensures that some water supply storage is reserved for future allocations. To accomplish this policy, the following criteria were used:
The Division's recommendations and the applicants' requests are summarized
in Table 2. The Division's allocation recommendation is no increase in
Chatham County's existing allocation and no allocation to the Cities of
Durham, Fayetteville, and Greensboro. All of these systems had a zero or
a small deficit with other available alternatives for their projected 2015
water demands.
The Division recommends proceeding with a public hearing for a 0.5 MGD
allocation for the Town of Holly Springs. Also, for the Towns of Apex,
Cary, Morrisville, and Wake County/RTP South, the Division recommends proceeding
with the interbasin transfer certification using the recommended allocation
amounts in Table 2 for doing the necessary environmental review.
Table 2. Water Supply Allocation Recommendations
Applicant |
Current Allocations (MGD) | Applicant Requests (MGD) | State Recommendation | |||
| Level I | Level II | System Request | Total1 | Recommendation | Total1 | |
| Chatham County | 4.0 | 2.0 | 7.0 | 13.0 | 0.0 | 6.0 |
| City of Durham | 25.0 | 25.0 | 0.0 | 0.0 | ||
| Fayetteville | 20.0 | 20.0 | 0.0 | 0.0 | ||
| Greensboro | 25.0 | 25.0 | 0.0 | 0.0 | ||
| Holly Springs | 4.5 | 4.5 | 0.5 | 0.5 | ||
| Apex & Cary2 | 16.0 | 29.0 | 45.0 | 5.0 | 21.0 | |
| Morrisville2 | 4.5 | 4.5 | 2.5 | 2.5 | ||
| Wake County/RTP2 | 3.5 | 3.5 | 1.5 | 1.5 | ||
| OWASA | 10.0 | No application submitted this round | 10.0 | |||
| Orange County | 1.0 | No application submitted this round | 1.0 | |||
| Totals | 20.0 | 13.0 | 118.5 | 151.5 | 9.5 | 42.5 |
1 This column shows the total allocations if all the current requests or recommendation were approved
2 Allocation is contingent on obtaining interbasin
transfer certification. The recommendations provided are for informational
purposes only at this time.
Table 3 provides a more detailed summary of each of the systems' projected
population and water use. The appendices provide details on each of the
systems.
The applicants for which an allocation is recommended and for which
interbasin transfer will be an issue include Holly Springs, Morrisville,
Cary/Apex, and RTP South. For all of these systems the responsibility would
be Cary's and Apex's for obtaining the interbasin transfer certification,
since they own the pipes at the point where the transfer occurs. However,
the rules also allow for another party involved in the transfer to assume
responsibility for certification, if approved by the Director of the Division
of Water Resources.
Holly Springs has requested to assume responsibility for certification
of the interbasin transfer associated with their allocation request. The
Division is going to approve their request for the following reasons. Holly
Springs has its own WWTP which discharges back into the Cape Fear River
basin, not the Neuse River basin. The estimated maximum daily transfer
is only 0.8 MGD, based on the 0.5 MGD allocation recommendation. Since
the Holly Springs interbasin transfer potential is only 0.8 MGD, well below
the 2.0 MGD certification threshold, no interbasin transfer certification
is needed at this time.
Table 3. Summary of Population and Water System Information1
| Applicant | Year |
Water System Population |
Water Use (MGD) |
Current System Yield
(MGD) |
System Deficit (MGD) |
Total Recommendation
(MGD) |
| Chatham County | 1995 | 7,200 | 0.9 | 6.6 | ||
| 2015 | 35,700 | 5.3 | 6.0 | 0.0 | ||
| 2025 | 51,800 | 7.7 | 6.0 | 1.7 | ||
| City of Durham | 1995 | 141,000 | 25.8 | 37.0 | ||
| 2015 | 243,000 | 38.0 | 37.0 | 1.0 | 0.0 | |
| 2025 | 267,000 | 40.3 | 37.0 | 3.3 | ||
| Fayetteville | 1995 | 159,000 | 22.1 | 66.0 | ||
| 2015 | 295,000 | 42.2 | 66.0 | 0.0 | ||
| 2025 | 308,000 | 43.2 | 66.0 | |||
| Greensboro | 1995 | 197,000 | 34.6 | 36.0 | ||
| 2015 | 218,000 | 48.0 | 64.1 | 0.0 | ||
| 2025 | 227,000 | 54.9 | 64.0 | |||
| Holly Springs | 1995 | 3,500 | 0.3 | 1.1 | ||
| 2015 | 27,100 | 2.8 | 2.4 | 0.4 | 0.5 | |
| 2025 | 35,800 | 3.6 | 2.4 | 1.2 | ||
| Apex & Cary | 1995 | 77,800 | 10.7 | 16.0 | ||
| 2015 | 235,000 | 20.9 | 16.0 | 4.9 | 5.0 | |
| 2025 | 278,000 | 24.9 | 16.0 | 8.9 | ||
| Morrisville | 1995 | 2,090 | 0.5 | 1.0 | ||
| 2015 | 12,200 | 2.6 | 0.0 | 2.6 | 2.5 | |
| 2025 | 16,500 | 3.5 | 0.0 | 3.5 | ||
| Wake County
(RTP South) |
1995 | Not Applicable | 0.005 | 1.0 | ||
| 2015 | Not Applicable | 1.6 | 0.0 | 1.6 | 1.5 | |
| 2025 | Not Applicable | 2.1 | 0.0 | 2.1 |
1 The data presented in this table is the
Division of Water Resources independent analysis of population and water-use
projections.
Contract Changes
The Division is proposing to modify how the contracts between the State
and local governments are written. The Division's proposed change is to
modify the contracts with local governments to exclude the maximum rate
of withdrawal and base the allocation only on storage. This change will
make the contract more consistent with what the water systems are actually
purchasing. Systems are purchasing water supply storage and not a guaranteed
rate of withdrawal. Also this change will allow the systems to be able
to increase withdrawals to meet their peak demands as long as the annual
average withdrawal rate does not exceed their allocation amount and their
storage is not depleted. The contracts will, however, indicate the estimated
safe yield provided by the storage allocated to an applicant. To protect
the reservoir from potential over use, DWR will not only rely on the Division
of Environmental Health's treatment capacity and system expansion approval
process, but will also require a water shortage response plan to be completed
and approved by both the Corps and the State. An approved plan needs to
be completed before any level II allocations are approved for level I.
Existing level I allocations need an approved plan within 1 year of the
contract modification. Also, DWR will work with the Corps to make available
over the Internet the storage and withdrawal records for everyone's review.
The following is an example of how the contract would be modified:
Storage Amount. The Allocation Holder, subject to this contract
with the State, has the right to use ten (10) percent of the water supply
storage capacity of the project, estimated to be four thousand five hundred
and eighty (4,580) acre-feet. The estimated safe yield from this storage
is approximately ten (10) million gallons per day (MGD). When the Allocation
Holder's storage is depleted, the Allocation Holder will have the right
to withdraw ten (10) percent of the portion of net inflow allocated to
water supply (10 percent of 32.62 percent equals 3.262 percent). The Government
and the State will maintain records on the amount of water supply available
in the water supply pool, and will inform each Allocation Holder of the
amount of water available in its portion of that pool.
Within one (1) year of receiving a level I water supply allocation,
the allocation holder will develop a water shortage response plan that
is approved by both the Government and the State.
Watershed Diversions
The existing administrative rule limits water supply allocations that
will result in diversions out of the lake's watershed to 50 percent of
the 100 MGD total water supply yield. The EMC may review and revise this
limit based on experience in managing the lake and on the effects of changes
in the lake's watershed that will affect its yield. Currently, 19.4 percent
of the 100 MGD yield is diverted out of the lake's watershed.
This administrative rule has raised a number of water quality and public
health issues during the allocation process. A computer model is going
to be developed as part of the interbasin transfer certification process.
Division staff will use the model to determine if a joint study with the
Corps, the Division of Water Quality, the Division of Environmental Health,
and DWR is needed to reconsider the 50 percent rule. For this current round
of allocations the limit does not need to be revised.
Watershed Transfers
The Jordan Lake watershed is that portion of the Haw River sub-basin
upstream of Jordan Lake Dam. To protect the yield of Jordan Lake for water
supply and water quality purposes, the current rules limit allocations
that will result in diversions out of the lake's watershed to 50 percent
of the total water supply yield, or 50 MGD. This provision is specific
to the lake's watershed because water returned below the dam does not replenish
the reservoir's water supply and water quality pools. The EMC may review
and revise this limit based on experience in managing the lake and on the
effects of changes in the lake's watershed that will affect its yield.
This 50-MGD limit refers to annual average diversions, since yields
are typically based on annual averages. Table 4 summarizes the estimated
diversions out of the lake's watershed, based on the 2015 demand projections
and the recommended allocation amounts. As shown, 26.5 MGD of the 42.5
MGD total recommended allocation would be diverted out of the lake's watershed
as of 2015, leaving 23.5 MGD of the water supply storage still available
for future allocations outside the lake's watershed under the current 50-MGD
limit.
Table 4. Estimated 2015 Jordan Lake Watershed Diversions
| System | Total Recommended
Allocation (MGD)1 |
2015 Watershed
Diversion (MGD) |
| Chatham County | 6.0 | 3.0 |
| Durham | 0.0 | 0.0 |
| Fayetteville | 0.0 | 0.0 |
| Greensboro | 0.0 | 0.0 |
| Holly Springs | 0.5 | 0.5 |
| Morrisville | 2.5 | 2.5 |
| Cary/Apex | 21.0 | 18.3 |
| Wake/RTP South | 1.5 | 1.2 |
| Orange County 2 | 1.0 | 1.0 |
| OWASA 2 | 10.0 | 0.0 |
| TOTAL | 42.5 | 26.5 |
1 Includes existing allocation amounts
2 Existing allocation holder, but did
not apply for additional allocation
Interbasin Transfers
Since the initial Jordan Lake allocations were made, a new regulatory framework has been established by the legislature for evaluating interbasin transfers. This law (G.S. 143-215.22I) is intended to regulate large surface water transfers by requiring a certificate from the Environmental Management Commission (EMC). The law applies to anyone initiating a transfer of 2 million gallons per day (MGD) or more from one river basin to another and to anyone increasing an existing transfer by 25 percent or more, if the total including the increase is 2 MGD or more. However, if a transfer facility existed or was under construction on July 1, 1993, a certificate is not required up to the full capacity of that facility to transfer water, regardless of the amount of the transfer.
If an existing transfer was approved by the EMC in a certificate issued
under G.S. 162A-7 prior to July 1, 1993, any increase above the amount
approved will require certification under G.S. 143-215.22I. Cary and Apex
have such a certificate, allowing them to transfer up to 16 MGD from the
Cape Fear River basin to the Neuse River basin. Any increase in this amount
would require certification.
The amount of a transfer is defined by the rules (T15A: 02E .0400) as
the amount of water moved from the source basin to the receiving basin,
less the amount of water returned to the source basin. Therefore, any water
consumption that occurs in the receiving basin would be considered a transfer,
even if the remaining wastewater is discharged back to the source basin.
In addition, certification is based on maximum daily transfer amounts,
not average daily amounts.
The statute defines 38 sub-basins across the state. Only transfers from
one of these defined sub-basins to another defined sub-basin is subject
to regulation. However, under the statutes, if water is discharged either
downstream or upstream from the point where it was withdrawn, it is not
considered a transfer. For example, if a system in the Neuse River basin
received an allocation from Jordan Lake (Haw River sub-basin) and then
discharged its treated wastewater directly into the Cape Fear River, this
would not be a transfer under the statutes. However, if that same system
discharged its wastewater into a tributary of the Cape Fear River instead
of directly into the Cape Fear River, that would be a transfer under the
statute. In other words, if the water would have naturally flowed past
the discharge point, as described in the rules, the transfer would not
be subject to regulation.
Recommendations Involving Interbasin Transfers
The applicants for which an allocation is recommended and for which
interbasin transfer is an issue include Holly Springs, Morrisville, Cary/Apex,
and RTP South. The estimated maximum daily demands (MDDs) and potential
maximum daily interbasin transfer amounts for 2000 and 2015 are summarized
in Table 5 below. Estimates for both 2000 and 2015 are given since transfers
are projected to decrease after 2000 when the West Cary WWTP is expected
to come on-line in either the Haw or Cape Fear River sub-basin.
Table 5. Estimated Potential Interbasin Transfers
| System | Total Recommended
Allocation (MGD)1 |
Jordan Lake
MDD (MGD) |
Potential Interbasin
Transfer (MGD) |
||
| 2000 | 2015 | 2000 | 2015 | ||
| Holly Springs | 0.5 | 0 | 0.8 | 0 | 0.8 |
| Morrisville | 2.5 | 1.8 | 3.6 | 1.8 | 3.5 |
| Cary/Apex | 21 | 20.3 | 38.4 | 17.7 | 15.3 |
| RTP South | 1.5 | 0.9 | 2.6 | 0.7 | 0.0 |
1 Includes existing allocation amounts
The Holly Springs estimate reflects DWR's recommended 0.5 MGD allocation,
not their requested allocation of 4.5 MGD. Note also that the Cary/Apex
2015 MDD and transfer are the applicant's estimates which were based on
their projected 2015 average daily demand of 24 MGD. Since this demand
exceeds the recommended 21 MGD total allocation for Cary/Apex, the transfer
may be less, depending on the West Cary WWTP discharges.
The rule stipulates that responsibility for obtaining certification
for a transfer belongs to the owner of the pipe where it crosses the sub-basin
divide. For all of the systems listed above, that responsibility would
be Cary/Apex's, since they own the pipes at the point where the transfer
occurs. However, the rules also allow for another party involved in the
transfer to assume responsibility for certification, if approved by the
Director of the Division of Water Resources.
Holly Springs has asked to assume responsibility for certification of
the transfer associated with its allocation request. DWR intends to approve
that request for the following reasons. Cary/Apex, Morrisville, and RTP
South effectively act as a regional water system, since Morrisville and
RTP South will rely totally on Cary/Apex for water and wastewater services
for their allocated water. Holly Springs, on the other hand, has its own
WWTP which discharges back into the Cape Fear River basin, not the Neuse
River basin as the others do. The estimated maximum daily transfer for
Holly Springs is only 0.8 MGD, based on the recommended 0.5-MGD allocation.
Since the certification threshold for transfers is 2.0 MGD, EMC certification
will not be required for this transfer.
The combined estimated transfer for Cary/Apex, Morrisville, and RTP
South is 20.2 MGD for 2000 and 18.8 MGD for 2015. Cary/Apex's current transfer
certificate is for 16 MGD.
For water supply allocations requiring interbasin transfer certification,
the major milestones in the process and a general time frame are described
below:
Information item at the EMC Water Quality Committee
meeting, March 1997.
This would occur concurrent with the public hearing
process for non-interbasin transfer allocations.
The applicant is responsible for arranging the scoping
meetings, preparing the study plans, and conducting the studies with DWR
oversight. The time needed to develop the environmental documentation will
depend upon the amount of the transfer and the issues identified in the
scoping meeting(s). Depending upon the complexity of the issues, these
tasks will likely range from 12 to 24 months in length.
A Cape Fear River Basin hydrologic model is planned that will assist
decision-makers involved in the allocation and interbasin transfer processes,
as well as provide a sound basis for developing water shortage response
plans for Jordan Lake. The goal is to openly develop an analytical tool
accepted by all basin stakeholders that can be used in developing consensus
on a wide range of basin issues. The model would be developed by a qualified
consultant hired by the Division of Water Resources. Funding for the model
will come primarily from applicants and current allocation holders.
A Steering Committee will be created during the first quarter of 1997
to assist DWR in guiding the model development, including consultant selection,
formulating model objectives, and locating and providing data. The Steering
Committee will consist of :
current allocation holders and applicants
US Army Corps of Engineers
Council of Government (COG) representation from upper, middle, and lower basin
industrial representative
agricultural representative (extension service)
environmental/conservation representative
Applications of the model may include:
confirm Jordan Lake's yield/reliability
evaluate the 50-percent limit on allocations out of the watershed
evaluate flow-related impacts of interbasin transfers
evaluate the impacts of new or expanded water supply withdrawals
water shortage response planning
study recreational impacts
provide input to water quality models
Appendix A. Chatham County A-1
Appendix B. City of Durham B-1
Appendix C. City of Fayetteville C-1
Appendix D. City of Greensboro D-1
Appendix E. Towns of Apex and Cary E-1
Appendix F. Town of Holly Springs F-1
Appendix G. Town of Morrisville G-1
Appendix H. Wake County / Research Triangle Park H-1
Appendix I. Summary of Public Comments on the Process I-1
Appendix J. Population and Water Use Projection Methodology J-1
Appendix K. North Carolina Administrative Code Section
T15A:02G.0500 Allocation of Jordan Lake Water Supply Storage
K-1
Appendix L. North Carolina Statute G.S. 143-215.22G
and
G.S. 143-215.22I Regulation of Surface Water Transfers L-1
Appendix M. North Carolina Administrative Code Section T15A:02G.0400 Regulation of Surface Water Transfers M-1
Appendix N. Contacts For Additional Information
N-1
Overview and System Recommendation
Chatham County is located in the central piedmont of North Carolina.
As a neighbor of the booming research triangle region, the County is beginning
to experience some of the same rapid development. The County's water system
is divided into three sections: the Southwest Chatham Water System, the
East Chatham Water System and the North Chatham Water System. Combined,
the systems serve about 17 percent of Chatham County, including several
small municipalities.
The system currently relies on an existing 6 MGD allocation from Jordan
Lake and purchases from the Town of Siler City, Goldston-Gulf Sanitary
District, and the City of Sanford. The County has requested an additional
Level I allocation of 3.0 MGD and Level II allocation of 4.0 MGD based
on average daily demand in the year 2025. This request would give the County
a total allocation of 13 MGD.
The Division recommends, based on average daily demand in 2015, no additional
allocation.
Population and Water Use Projections
The 1995 service population of Chatham County was 7,180. In 2015, Chatham
County projects its service population will grow to 78,545 with an average
daily demand of 11.3 MGD. In an addendum to their application, the County
offered several growth scenarios to support their projections. The County
suggested the following factors will influence its growth: 1) increased
building activity, 2) improved highway access, and 3) innovative waste
treatment solutions. The County derived growth rates from building permit
information for both the county as a whole and for a high-growth census
tract in the northeast corner of the county. The County's preferred scenario
projected population based on the higher growth rate for years 1995 to
2005, and on the county growth rate for years 2010 to 2015.
The County also expects to increase its service area, eventually supplying
water to most of the county and some of the existing municipal water systems.
The County has provided letters from water systems in Siler City, Pittsboro,
and Goldston indicating an interest in having Jordan water as a future
alternative. By 2015, the County predicts it will serve 75 percent of the
total county population.
The Division developed an independent forecast of service population
for comparison purposes. The forecast was based on county population estimates
by the Office of State Planning (OSP). The Division adjusted the OSP figures
to reflect the recent county building permit information. This adjustment
assumes the county population will grow at a rate of 3.75 percent from
1995 to 2005. The difference between the original OSP 2005 population and
the adjusted 2005 population was then added to the remaining OSP forecast
years to be consistent with the adjustment. This results in a county population
forecast which reflects both short-term building activity and long-term
OSP growth assumptions.
The Division assumed that the County's service population would increase
linearly from its current level to 75 percent of total county population
by 2025. In order to justify more rapid expansion, the Division would require
evidence of formal arrangements with those systems the County anticipates
eventually serving. In 2015, service population is estimated to reach 56
percent of county population, or 35,700. Table A-1 summarizes population
projections.
Table A-1. Population Projections
Year |
County Population | Percent Served | Service Population | |||
| Applicant | DWR | Applicant | DWR | Applicant | DWR | |
| 1995 | 42,914 | 42,914 | 17% | 17% | 7,180 | 7,180 |
| 2000 | 56,492 | 50,900 | 31% | 26% | 17,682 | 13,500 |
| 2005 | 74,366 | 60,400 | 46% | 36% | 34,112 | 21,300 |
| 2010 | 88,250 | 61,500 | 60% | 46% | 53,329 | 28,200 |
| 2015 | 104,726 | 64,200 | 75% | 56% | 78,545 | 35,700 |
| 2020 | 66,500 | 65% | 43,400 | |||
| 2025 | 69,000 | 75% | 51,800 | |||
Chatham County projects a 2015 average daily demand of 11.3 MGD. Projections
were based on their forecasts of service population and per capita use.
The County assumed per capita use would increase from current levels as
additional industries are connected to the system.
The Division's water use projections are based on service population
and per capita water use. For Chatham County, the Division assumed per
capita demand would drop about 10 percent due to conservation in all categories
except industrial. Since the County currently does not supply any industrial
customers, per capita use in this category was raised to 20 GPCD to provide
for a moderate level of new industry. Unaccounted water use, which the
County reported as 0.0 MGD, was also increased to 10 percent of total water
use to allow for typical transmission losses. The net effect of these adjustments
is a higher per capita rate for new water use.
Table A-2 summarizes the average daily demands and computed deficits
for Chatham County. The Division estimates a 2015 demand of 5.3 MGD. Compared
with the 2015 safe yield of 6.0 MGD, the County should have a small surplus
in 2015. The estimated demand in 2005 (3.1 MGD), also falls well under
80 percent of the available yield -- a common threshold for water supply
planning. Based on these results, the Division recommends no additional
allocation at this time. The Division also recommends that the County proceed
with formalizing arrangements with other county systems that may require
Lake Jordan water in the future.
Table A-2. Water Use Projections
| Year | Overall Per Capita (GPCD) | Average Daily Demand (MGD) | Safe Yield
(MGD) |
System Deficit (MGD) | |||
| Applicant | DWR | Applicant | DWR | Applicant | DWR | ||
| 1995 | 127 | 127 | 0.9 | 0.9 | 6.6 | - | - |
| 2000 | 142 | 145 | 2.5 | 2.0 | 6.6 | - | - |
| 2005 | 144 | 147 | 4.9 | 3.1 | 6.6 | - | - |
| 2010 | 144 | 148 | 7.7 | 4.2 | 6.6 | 1.1 | - |
| 2015 | 144 | 148 | 11.3 | 5.3 | 6.0 | 5.3 | - |
| 2020 | n/a | 148 | n/a | 6.4 | 6.0 | n/a | 0.4 |
| 2025 | n/a | 149 | n/a | 7.7 | 6.0 | n/a | 1.7 |
Current Water Supply Sources
Chatham County's current water supplies include a 6.0 MGD allocation
from Jordan Lake, and contracted purchases from the Town of Siler City,
Goldston-Gulf Sanitary District, and the City of Sanford. The County also
maintains an emergency connection with Pittsboro. The total safe yield
of these supplies is 6.63 MGD. The County anticipates that the purchase
contracts will terminate by 2015. Table A-3 summarizes the County's water
sources.
Chatham County's water system is divided into three sections. The North
Chatham Water System serves the Bynum, Fearington Village and Governor's
Club area, and the new 3 MGD water treatment plant on Jordan Lake. The
Southwest Chatham System serves Bennett, Bear Creek and Bonlee areas, and
purchases water from Siler City and Goldston-Gulf. The East Chatham Water
System serves the Moncure, Haywood and Corinth areas, and purchases water
from Sanford. The County is pursuing interconnection of the three systems
to form a county-wide system.
Table A-3. Current Water Supply Sources
| Source | River Basin | Type | Safe Yield
(MGD) |
Water Quality |
| Jordan Lake | Haw | Surface | 6.000 | Good |
| Siler City | Rocky | Purchase | 0.166 | Good |
| Goldston-Gulf | Deep | Purchase | 0.160 | Good |
| Sanford | Cape Fear | Purchase | 0.300 | Good |
| Pittsboro | Haw | Purchase | Not specified | Good |
| TOTAL | 6.63 | |||
Alternative Sources
Chatham County lists a number of alternatives to a Jordan Lake allocation.
Table A-4 summarizes the alternatives for the Southwest and East Chatham
water systems. The North Chatham System currently has the capacity to treat
3.0 MGD of Jordan Lake water. The County did not provide unit costs for
withdrawing and treating an additional allocation.
Table A-4. Alternative Water Supply Sources
| Alternative | Safe Yield
(MGD) |
Cost to Develop ($/1000 Gal) | Water Quality | Environ-mental Impacts | Institutional Impacts |
| Southwest Chatham System | |||||
| Jordan Lake | 1.0 | 2.30 | Good | Major | Typical |
| Continue Bulk Purchase | 0.3 | 2.67 | Good | Minor | Typical |
| New Wells | Insuff. | - | - | - | - |
| Deep River Treatment Plant | 1.0 | 2.64 | Good | Major | Typical |
| East Chatham System | |||||
| Jordan Lake | 0.5 | 2.46 | Good | Major | Typical |
| Continue Bulk Purchase | 0.3 | 3.20 | Good | Minor | Typical |
| New Wells | Insuff. | - | - | - | - |
| Cape Fear River Treatment Plant | 0.5 | 3.27 | Good | Major | Typical |
Conservation and Demand Management
At the present time, Chatham County does not have a formal water conservation
policy. The County performs a monthly water accounting to detect potential
leaks. The County is in the process of studying water conservation options
including a revised plumbing code, a conservation ordinance, rate structure
incentives, water reuse, and water shortage response plan.
Plans to use Jordan Lake
Chatham County has applied for a Level I allocation of 3.0 MGD, and
a Level II allocation of 4.0 MGD. The County already operates a treatment
facility on Lake Jordan and has secured a share in the Apex/Cary intake
facility. The County foresees Jordan Lake becoming the primary water source
for the entire county. In order to provide Jordan Lake water on a county-wide
basis, the County will have to expand the water treatment plant and construct
transmission mains interconnecting the three water systems. The County
plans to phase in these upgrades over a twenty or thirty-year planning
period.
Chatham County has in place a water quality monitoring plan to test
both raw and finished water taken from Jordan Lake. All testing will be
in accordance with the North Carolina Department of Environment, Health,
and Natural Resources, Division of Environmental Health, and the U.S.-EPA.
Watershed and Interbasin Transfers
Portions of Chatham County lie in three different river basins: the
Haw, Deep, and Cape Fear. Interbasin transfers would occur primarily from
consumptive use in the Deep and Cape Fear basins. The Division estimates
that about 40 percent of a future Jordan Lake allocation would be transferred
out of basin. The out-of-watershed diversion would be about 50 percent
of the allocation amount. Based on the recommendation of no additional
allocation, an interbasin transfer certificate is not required.
Overview and System Recommendation
The City of Durham is located in Durham County in the northern piedmont.
As part of the prosperous research triangle region, Durham anticipates
continued strong growth. Durham's water system serves the City and some
outlying areas including parts of Research Triangle Park. The system relies
on two water supply reservoirs, Lake Michie and Little River Lake.
The City of Durham has requested a Level II allocation of 25 MGD, based on maximum daily demand in 2025. The Division's recommends, based on average daily demand in 2015, no additional allocation.
Population and Water Use Projections
The 1995 service population of Durham was 141,000. In 2015, Durham projects
a service population of 257,000 with an average daily demand of 40.9 MGD.
Durham based its water demand projection on a historical 3 percent growth
rate.
The Division developed an independent forecast of service population
for comparison purposes. The forecast was based on the Office of State
Planning's (OSP) forecast of county population. Based on planned service
expansions, the Division accepted Durham's service population forecast
through the year 2005. After the year 2005, though, Durham's estimate exceeded
the OSP county forecast. The Division assumed Durham's service population
would not exceed total county population, so therefore used OSP county
population figures for years 2010 to 2025. Table B-1 summarizes population
projections.
Table B-1. Population Projections
Year |
OSP County Population 1 | Service Population | |
| Applicant | DWR | ||
| 1995 | 192,096 | 141,000 | 141,000 |
| 2000 | 203,295 | 195,300 | 195,000 |
| 2005 | 215,975 | 215,500 | 216,000 |
| 2010 | 229,197 | 237,500 | 238,000 |
| 2015 | 242,727 | 257,700 | 243,000 |
| 2020 | 256,661 | 279,300 | 257,000 |
| 2025 | 267,197 | 301,000 | 267,000 |
1 OSP forecasts county population out to 2020.
An estimate of 2025 population was derived by linear regression.
The Division's water use projections are based on service population
and per capita water use. For Durham, the Division assumed per capita demand
in all categories would drop about 10 percent from 1995 levels. In the
residential category, the average of several reporting years was used in
place of the 1995 value, which was unusually high. Unaccounted water use
was assumed to be 15 percent of total water use, based on Durham's current
level of metering. The net effect of these adjustments was to reduce overall
per capita use.
Table B-2 summarizes the average daily demands and computed deficits
for Durham. The Division estimates a 2015 demand of 38.0 MGD. Compared
with the 2015 safe yield of 37.0 MGD, Durham should have a deficit of about
1.0 MGD in 2015. A comparison was also made between Durham's 2005 demand
and available yield to determine if Durham has sufficient time to plan
for new supplies. Durham's 2005 demand exceeds 80 percent of safe yield
-- a common threshold for water supply planning. This suggests that Durham
needs to begin the planning process for its next water supply in the near
future.
Based on Durham's available alternatives for future water supply, the
Division recommends no additional allocation at this time. However, the
Division recommends that Durham immediately begin exploring all alternatives
to Jordan Lake.
Table B-2. Water Use Projections
| Year | Overall Per Capita Use (GPCD) | Average Daily
Demand (MGD) |
Safe Yield
(MGD) |
System Deficit (MGD) | |||
| Applicant | DWR | Applicant | DWR | Applicant | DWR | ||
| 1995 | 182 | 183 | 25.6 | 25.8 | 37.0 | - | - |
| 2000 | 151 | 168 | 29.4 | 32.9 | 37.0 | - | - |
| 2005 | 154 | 163 | 33.2 | 35.2 | 37.0 | - | - |
| 2010 | 156 | 159 | 37.0 | 37.8 | 37.0 | - | 0.8 |
| 2015 | 159 | 156 | 40.9 | 38.0 | 37.0 | 3.9 | 1.0 |
| 2020 | 160 | 154 | 44.7 | 39.4 | 37.0 | 7.7 | 2.4 |
| 2025 | 161 | 151 | 48.5 | 40.3 | 37.0 | 11.5 | 3.3 |
Current Water Supply Sources
Durham's current water supplies include Lake Michie and Little River Lake with a total 50-year safe yield of 37 MGD. Both sources are located in the Neuse River Basin and provide high quality drinking water. Durham also maintains an emergency raw water intake on the Eno River. Table B-3 summarizes Durham's current water sources.
Table B-3. Current Water Supply Sources
| Source | River Basin | Type | Safe Yield
(MGD) |
Water Quality |
| Lake Michie | Neuse | Surface | 19 | Excellent |
| Little River Lake | Neuse | Surface | 18 | Excellent |
| Eno River | Neuse | Surface | n/a | Good |
| TOTAL | 37 | |||
Alternative Sources
In their application, Durham lists two water supply alternatives to
Jordan Lake: Lake Michie expansion and Teer Quarry. The Lake Michie expansion
proposes raising the lake level to 380 M.S.L. The expansion would provide
an additional 25 MGD safe yield. The City has already begun purchasing
property around the lake to preserve land for future water supply and enhanced
buffer areas. 1995 total development costs for this alternative are $2.12
per 1000 gallons.
Teer Quarry is an inactive quarry site that could be used for off-stream
storage of 2 to 3 billion gallons of water. An intake on the Eno River
would be used to fill the pit. This project would provide about 8 MGD of
intermittent supply to help meet summer peak demands. Availability of the
site for water supply purposes is uncertain at this time. 1995 total development
costs for this alternative are $1.56 per 1000 gallons.
Durham estimates that development of transmission facilities for a Jordan
Lake allocation would cost $1.47 per 1000 gallons. Lower costs are expected
if bulk purchases are contracted through Cary or OWASA. Jordan Lake represents
the least expensive alternative. Table B-4 lists Durham's alternatives.
Table B-4. Alternative Water Supply Sources
| Alternative | Safe Yield
(MGD) |
Cost to Develop ($/1000 Gal) | Water Quality | Environ-mental Impacts | Institutional Impacts |
| Lake Michie Expansion | 25 | 2.12 | Excellent | Moderate | Typical |
| Teer Quarry | 8 | 1.56 | Good | Minor | Typical |
| Jordan Lake | n/a | 1.47 | Good | Minor | Simple |
Conservation and Demand Management
Durham's conservation policy is based on two documents. The first is
Durham's Water Conservation Ordinance which meets the requirements of a
Water Shortage Response Plan under the State's local water supply planning
process. The ordinance outlines voluntary and mandatory conservation measures
for four levels of water shortage. The other document is a report by the
Water Resources Research Institute on water conservation potential in Durham.
The report is intended to guide development of future conservation programs,
but the report has not been formally adopted as a program.
Durham currently maintains two full-time water conservation staff positions.
Durham also notes efforts to develop a reclaimed wastewater market.
Plans to use Jordan Lake
Durham has outlined two options for using a Jordan Lake allocation.
The first option is to arrange a bulk purchasing contract with Cary or
Orange Water and Sewer Authority (OWASA). Of the two, only Cary has an
operating intake facility. The second option is to construct all facilities
necessary for transmission of water from the existing intake on the east
side of Jordan Lake to Durham's own treatment facility. If water use continues
to grow at current rates, Durham would begin preparing for the project
around 2005. Durham states that excess water could possibly be made available
for sale to Hillsborough or Butner.
Durham states that they will develop a water quality monitoring plan
based on regulations of the N.C. Department of Environment, Health, and
Natural Resources, Division of Environmental Health, and the U.S. EPA.
Watershed and Interbasin Transfers
Durham currently withdraws all of its water from Lake Michie and Little
River Lake in the Neuse Basin. About 63 percent of this withdrawal is consumed
in or discharged into the Cape Fear Basin. A Jordan Lake allocation to
Durham would represent a transfer from the Cape Fear Basin to the Neuse
Basin, therefore offsetting part of Durham's existing interbasin transfer.
Under current rules, an interbasin transfer certificate would not be required
in this case.
A Jordan Lake allocation would also not cause an out-of-watershed diversion
since Durham would consume more water in the Cape fear Basin than it would
withdraw.
Appendix C. City of Fayetteville
Overview and System Recommendation
The City of Fayetteville is located in Cumberland County in the southern
piedmont. The City's Public Works Commission (PWC) provides water to about
54 percent of Cumberland County, including the City and towns of Hope Mills
and Spring Lake.
The system relies on withdrawals from the Cape Fear River and impoundments
on Little Cross Creek and Big Cross Creek. PWC has requested a Level II
allocation of 20 MGD, based on average daily demand in the year 2025. Based
on average daily demand in 2015, the Division recommends no allocation
for PWC at this time.
Population and Water Use Projections
PWC's service population in 1995 was 158,600. In 2015, PWC projects
a service population of 295,300 with average daily demand of 53.6 MGD.
PWC assumes that with service area expansions and modest growth, it will
serve about 86 percent of Cumberland County's population in 2015 (based
on previous OSP forecasts). PWC also plans to continue to supply emergency
water to Fort Bragg and recruit new industry to the area.
The Division developed an independent forecast of service population
for comparison purposes. The forecast was based on the Office of State
Planning's (OSP) forecast of county population. PWC's 2015 population forecast
was well documented and, when adjusted for the latest OSP forecast (1996
release), fairly conservative. The Division accepts PWC's 2015 service
population estimate of 295,300. Table C-1 summarizes population projections.
Table C-1. Population Projections
Year |
OSP County Population1 | Service Population | |
| Applicant | DWR | ||
| 1995 | 294,010 | 158,600 | 159,000 |
| 2000 | 314,833 | 203,200 | 203,000 |
| 2005 | 337,365 | 272,900 | 273,000 |
| 2010 | 354,856 | 284,100 | 284,000 |
| 2015 | 376,926 | 295,300 | 295,000 |
| 2020 | 393,578 | 301,000 | |
| 2025 | 415,422 | 307,600 | 308,000 |
1 OSP forecasts county population out to 2020.
An estimate of 2025 population was derived by linear regression.
The Division's water use projections are based on service population
and per capita water use. For PWC, the Division assumed per capita demand
would drop about 10 percent due to conservation in all categories except
industrial. Industrial per capita use was kept at current rates to accommodate
planned industrial expansions. The Division also assumed that PWC would
continue to maintain a 3.0 MGD emergency supply contract with Fort Bragg.
Unaccounted water use was reduced from 13 percent to 10 percent of total
water use based on PWC's stated conservation goal. The net effect of these
adjustments was to reduce overall per capita demand slightly from current
levels.
Table C-2 summarizes the average daily demands and computed deficits
for PWC. The Division estimates a 2015 demand of 43.5 MGD. Compared with
the 2015 safe yield of 66 MGD, PWC should have a surplus of about 22 MGD
in 2015. The estimated demand in 2005 (39.8 MGD), also falls well under
80 percent of the available yield -- a common threshold for water supply
planning. Based on these results, the Division recommends no additional
allocation for PWC at this time.
Table C-2. Water Use Projections
| Year | Overall Per Capita Use (GPCD) | Safe Yield
(MGD) |
Average Daily
Demand (MGD) |
System Deficit (MGD) | |||
| Applicant | DWR | Applicant | DWR | Applicant | DWR | ||
| 1995 | 140 | 155 | 66.0 | 22.1 | 22.1 | - | - |
| 2000 | 195 | 153 | 66.0 | 39.7 | 31.2 | - | - |
| 2005 | 183 | 146 | 66.0 | 49.9 | 39.8 | - | - |
| 2010 | 182 | 144 | 66.0 | 51.8 | 41.0 | - | - |
| 2015 | 182 | 143 | 66.0 | 53.6 | 42.2 | - | - |
| 2020 | 142 | 66.0 | 42.7 | - | - | ||
| 2025 | 191 | 140 | 66.0 | 58.8 | 43.2 | - | - |
Current Water Supply Sources
PWC's current water supplies include the Cape Fear River, a series of
four impoundments on Little Cross Creek, and a supplemental water supply
on Big Cross Creek. The total safe yield of these supplies is 66 MGD. To
aid the allocation process, the Division of Water Quality (DWQ) provided
a new safe yield estimate for the Cape Fear River at PWC's intake. DWQ
determined a safe yield of 60 MGD based on flow and water quality constraints.
Table C-3 summarizes Fayetteville's water sources.
Table C-3. Current Water Supply Sources
| Source | River Basin | Type | Safe Yield
(MGD) |
Water Quality |
| Cape Fear River | Cape Fear | Surface | 60 | Good |
| Little Cross Creek | Cape Fear | Surface | 5 | Good |
| Big Cross Creek | Cape Fear | Surface | 1 | Good |
| TOTAL | 66 | |||
Alternative Sources
PWC considers the Cape Fear River to be the only water source capable
of meeting additional future demands. PWC notes that they have investigated
ground water as an option, but regional aquifers are unable to provide
suitable yield. In their application, PWC provided no economic, environmental,
or institutional evaluation of any alternative.
Conservation and Demand Management
PWC has adopted a variety of programs to encourage water conservation, including:
Plans to use Jordan Lake
PWC has applied for a Level II allocation of 20 MGD. This allocation
would be made available to PWC downstream by additional spillway releases.
The existing intakes at the Hoffer Treatment Facility would be upgraded
by adding additional pumping capacity. PWC notes a number of other system
upgrades to accommodate additional water demands. Treated wastewater would
be discharged into the Cape Fear in the vicinity of Fayetteville.
PWC states that they would monitor water quality in accordance with
U.S.-EPA state regulations. PWC operates a state certified lab capable
of performing most of the required monitoring on an in-house basis.
Watershed and Interbasin Transfers
A Jordan Lake allocation to Fayetteville would not result in any interbasin
transfer. Fayetteville currently discharges all treated wastewater back
into the Cape Fear River. Any allocation, however, would be transferred
out of the watershed. Fayetteville's downstream location makes it difficult
to return wastewater to Jordan Lake.
Appendix D. City of Greensboro
Overview and System Recommendation
The City of Greensboro is located in Guilford County in the upper piedmont.
Greensboro's water system serves about 53 percent of Guilford County, including
the City and specific unincorporated areas of the County. The system currently
relies on water impounded in Lake Higgins, Lake Brandt, and Lake Townsend.
As a member of the Piedmont Triad Regional Water Authority, Greensboro
is pursuing the development of Randleman Lake to meet its water needs for
the next 50 years. The City's share of Randleman Lake's safe yield is 28.5
MGD. Pending the outcome of the NEPA process, Greensboro has sought a Jordan
Lake Level II allocation of 25 MGD, based on forecast demand in 2025. The
Division considers Randleman Lake to be a viable alternative to meet the
City's long-term water needs. Therefore, the Division recommends no allocation
at this time. However, it is possible for the City to maintain its request
for an allocation throughout the process until such time that a final decision
on construction of Randleman Lake is made. If it is ultimately decided
that Randleman Lake will not be built, the Division will reconsider the
City's allocation request.
Population and Water Use Projections
Greensboro's 1995 service population was 197,000. In 2015, Greensboro
projects a service population of 217,825 with an average daily demand of
48.0 MGD. Pending the outcome of the NEPA review of the Randleman Lake
project, the Division accepts the City's projections for the year 2015.
Including Greensboro's share of Randleman Lake, the City should have a substantial water surplus in 2015. Therefore, the Division's recommendation is no allocation at this time. If Randleman Lake is not approved for construction, the Division will re-evalua