2023 Annual Water Use Report
Section 1: Facility Information
Registrant: |
Duke Energy Progress, LLC |
Facility ID: |
0057-0017 |
Facility Name: |
Thorpe Hydro-electric Facility |
Facility Type: |
Energy |
County: |
Jackson |
Sub-Basin: |
Tuskasegee River (07-2) |
Mailing Address: |
151 Bad Creek Road Salem, SC 29676 |
Email: |
[email protected] |
Contact Person: |
Marcus Pitts |
Title: |
Lead EHS Professional |
Phone: |
864-304-9703 |
Fax: |
980-373-9198 |
Section 2: Withdrawal Information
2-A. Average daily withdrawal and maximum day withdrawal by month in million gallons per day (MGD)
Month |
# of Days Used |
Average Daily Withdrawal (MGD) |
Maximum Day Withdrawal (MGD) |
Month |
# of Days Used |
Average Daily Withdrawal (MGD) |
Maximum Day Withdrawal (MGD) |
Jan |
31 |
119.35 |
138.20 |
Jul |
31 |
56.83 |
126.96 |
Feb |
11 |
44.44 |
127.62 |
Aug |
31 |
49.47 |
99.28 |
Mar |
31 |
89.62 |
124.80 |
Sep |
13 |
10.93 |
38.33 |
Apr |
12 |
17.93 |
100.53 |
Oct |
26 |
35.69 |
96.55 |
May |
30 |
47.30 |
90.12 |
Nov |
30 |
47.28 |
65.20 |
Jun |
28 |
32.06 |
96.39 |
Dec |
9 |
21.42 |
126.03 |
2-B. Source Information - Please complete one row for each water withdrawal source. If any of your source information was imported from a previous year, please make sure you click edit and fill in the information left blank that is needed for the 2023 reporting year.
Source Name |
Source Type |
Average Daily |
Days Used |
Pumping Capacity (MGD) |
Lake Glenville - Hydro Intake |
Reservoir |
54.7 |
283 |
0.000 |
Section 3: Discharge Information
3-A. Average daily discharge and maximum day discharge by month in million gallons per day (MGD)
Month |
# of Days Discharged |
Average Daily Discharge (MGD) |
Maximum Day Discharge (MGD) |
Month |
# of Days Discharged |
Average Daily Discharge (MGD) |
Maximum Day Discharge (MGD) |
Jan |
31 |
119.35 |
138.20 |
Jul |
31 |
56.83 |
126.96 |
Feb |
11 |
44.44 |
127.62 |
Aug |
31 |
49.47 |
99.28 |
Mar |
31 |
89.62 |
124.80 |
Sep |
13 |
10.93 |
38.33 |
Apr |
12 |
17.93 |
100.53 |
Oct |
26 |
35.69 |
96.55 |
May |
30 |
47.30 |
90.12 |
Nov |
30 |
47.28 |
65.20 |
Jun |
28 |
32.06 |
96.39 |
Dec |
9 |
21.42 |
126.03 |
3-B. Please complete one row for each discharge method. If any of your discharge information was imported from a previous year, please make sure you click edit and fill in the information left blank that is needed for the 2023 reporting year.
Identifier or Permit Number |
Discharge Type |
Average Daily |
Days Discharged |
Discharge Capacity |
Lake Glenville - Hydro Flow-by |
Hydropower |
54.7 |
283 |
|
Section 4: Sub-Basin Transfer Information
Complete this section only if you withdraw or purchase water that is not returned to the sub-basin from which it was withdrawn.
4-A. Please complete one row for each transfer of surface water from one sub-basin to another. If any of your transfer information was imported from a previous year, please make sure you click edit and fill in the information left blank that is needed for the 2023 reporting year.
Description of Transfer |
Source Sub-Basin |
Receiving Sub-Basin |
Transfer Capacity |
No Transfers Listed. |
4-B. Enter the average daily and maximum day surface water transfer amount for each month in million gallons per day (MGD)
Month |
# of Days Transferred |
Average Daily Transfer (MGD) |
Maximum Day Transfer (MGD) |
Month |
# of Days Transferred |
Average Daily Transfer (MGD) |
Maximum Day Transfer (MGD) |
Jan |
|
|
|
Jul |
|
|
|
Feb |
|
|
|
Aug |
|
|
|
Mar |
|
|
|
Sep |
|
|
|
Apr |
|
|
|
Oct |
|
|
|
May |
|
|
|
Nov |
|
|
|
Jun |
|
|
|
Dec |
|
|
|
Do you have any comments?
|